This was the day we received the delivery of pre-cut metal fittings for the canopy details. Fine adjustment of these pieces had to be done by filing the holes. Then there was organising and labeling of the different fittings to the different detail corners. The fittings were also marked for further welding.

DSCF0478

DSCF0488

DSCF0485

DSCF0484

DSCF0480

Work on site continued with the building up of the front stairs…

IMG_0963

IMG_0979

And mounting more roof beams…

IMG_0975

IMG_0976

IMG_0972

IMG_0970